Module 3 of 12 · Project Finance

Cash, the Float & Collections

Reference guide to the cash pipe: who finances whom, the three numbers that measure it, the money that is not all Grace’s, and the collections sequence that protects the client relationship.

Finance Field Guide · companion to the Module 3 Overview & Quick Reference

Module Home  ›  Finance Field Guide

Optional depth. Read this for the cash, float, and collections mechanics behind the module. It is not required for the weekly 90 minutes.

Module 3 covers the pipeline, backlog to WIP to receivables to cash, and the three moves that push money through it. This guide answers one question: “Whose bank is Grace, and how fast does earned work become cash?” Every day in the pipe is a business decision, made deliberately or not.

1

Who is financing whom

The float: the interest-free loan Grace makes to the client

Payroll goes out every two weeks. Cash arrives months after the work. In between, the firm is the client’s bank, interest-free.

Grace’s $1.4M fee across a twelve-month design schedule earns roughly $115k in a typical month. The team works through the 31st. Pre-bills are reviewed by the 25th, the invoice goes out by the 7th, and terms are net-30. Even a client who pays on time pays about six weeks after the middle of the work. A client who pays “normally” stretches that past two months.

Earned / month
~$115k
Grace’s $1.4M over ~12 months
Work → cash
60 to 90 days
A typical client on normal terms Illustrative
Carried at all times
$230 to 350k
Two to three months of Oakhaven, financed by Grace
Payroll cycle
14 days
Fixed, regardless of client cash

That $230 to 350k is the float, money Grace has earned, has paid payroll against, and has not yet received, on one project. Across every active project in the studio, the float reaches the size of a small office’s annual payroll, permanently loaned out. The firm covers it with cash reserves or a line of credit, and a line of credit charges interest. The consequence is direct: the firm pays interest so the client can hold Grace’s money longer.

Every unbilled day is an interest-free loan extended on the firm’s behalf.
The float comes out of the profit slice
Only 15 to 20¢ of every net dollar survives as profit. Carrying cost, write-offs on aged invoices, and the hours spent chasing old money all come out of that same slice. A project can hold its margin all year and still lose part of it to slow cash.
2

BST column ⑦, in detail

Flow metrics: putting a number on the pipe

Module 2 covers scorecard columns ① to ⑥. This module covers column ⑦, the day counts. Three numbers measure the pipe.

MetricWhat it measuresWho owns it
Unbilled DaysHow long earned work sits as WIP before an invoice exists. The PM Speed Zone, with a number on it.The project manager, almost entirely. On the rhythm it runs in the single digits to ~15. Drifting, it reaches 45 or more, and the firm has financed the work.
Receivable Days (DSO)Invoice date to cash in the bank. DSO = receivables ÷ average daily billings.The project manager and the client together. Follow-up sets the pace.
Days to cashUnbilled + receivable days: the full length of the pipe, work to money.The single best measure of how well this module is being practiced on a project.

For scale: design-firm receivables industry-wide average around 70 days Illustrative · confirm in BST. A well-run project beats the industry average. Most of what makes cash slow is the invoice itself: sent late, sent wrong, or sent and never followed up.

The aging buckets: each one triggers a defined action

AgeWhat it usually meansGRACE MOVE
0 to 30Normal. The invoice is moving through approval.Accounting confirms receipt and approval within the first week. One short message.
31 to 60Stuck, not refused. Most “late” invoices are sitting in someone’s approval queue or missing a PO number.Accounting monitors and asks specifically: “Is anything holding the March invoice?” Fix the cause rather than re-sending.
61 to 90A real problem is forming: an unvoiced dispute, or a client cash issue.PM involvement typically requested. Call rather than email. Name the number and ask what is in the way. PIC informed.
90+Collection probability is falling every week. This is now a firm-level exposure.Leadership engaged. The contract’s remedies, including pausing work, are considered as a deliberate decision.
?  A project shows 12 unbilled days and 78 receivable days. Where does the effort go?

The Speed Zone is clean. Billing is on the rhythm. The delay is downstream: 78 receivable days means invoices go out and receive no follow-up. The move is Collect it: confirm approval on the newest invoice, and make the call on anything past 60.

3

The money that is not all Grace’s

Consultants & retainage

Half the Oakhaven fee was never Grace’s. The billing rhythm is the structural engineer’s payroll.

Oakhaven’s total design fee is $2.8M. Consultants carry $1.4M of it. That money moves through Grace: the consultant bills Grace, Grace bills the client for the full month’s work, and, where the contracts say pay-when-paid, the consultant is paid when the client’s cash arrives. Follow the chain: the invoice sits two weeks in WIP → the client pays six weeks later → the structural engineer waits two months for completed work. The billing habit sets the consultant’s cash flow.

Retainage: the last 10% has a contract clause
Some agreements hold 5 to 10% of every invoice until completion or a defined milestone. Where the contract does, the last 10% is held pending a release the project manager triggers: final deliverables accepted, punch items closed, release invoiced. Confirm at kickoff whether the contract holds retainage and what releases it, then put the release on the closeout checklist. Retainage releases only when it is invoiced.
Module 4 is where this gets decided. Net-30 or net-60, retainage or none, pay-when-paid or pay-regardless: the payment terms were set before invoice #1 was sent. On any project, read the payment clause as closely as the scope: Owning the Project →
4

Relationship work, not dunning

The collections craft

The collections call is a service, the same reframe as the fee conversation. Invoices stall in approval workflows rather than in bad faith. Surfacing a problem in week two helps the client.

Most PMs avoid the money follow-up for the same reason they absorb scope changes: it feels like an imposition. A client whose AP process stalled an invoice wants to know before it becomes a quarter-old balance. The craft is a rhythm, an early touch, and a fixed escalation ladder:

Lines to use
Day 7: “Wanted to make sure the March invoice landed and nothing in it needs clarifying before it goes through your approval.”
Day 45: “Our records show March still open. Is anything holding it up on your end? Happy to fix or re-send whatever is needed.”
Day 60: “I would rather ask directly than let this get awkward. Can we get March scheduled for payment this cycle? If something is wrong with the invoice, I want to know today.”

Each line gives the client clarity and a clean next step. Never go silent on money. Silence converts a process delay into an awkwardness, and an awkwardness into a write-off. A clean money relationship is part of the client’s experience of Grace, and value multiplies performance by experience.

The archetypes, at day 60
The Competent Coordinator forwards the aging report to accounting and considers it handled. The Obsessed Designer will “get to it after the deadline” at every deadline. The People Pleaser will not “bother” the client about money and finances them instead. The Accountable Owner treats the money conversation as part of the client relationship, not a breach of it.
5

A preview of the plan

Forecasting cash: every invoice has a date before the work starts

Module 2 covers the planned earned-value curve, how the fee will be earned across the schedule. Shift that curve twice to get the firm’s cash forecast: earned work becomes a billing curve on the invoice rhythm, and billings become a cash curve offset by days-to-cash. That is how the firm predicts in June whether November makes payroll.

Two consequences follow for the project manager: percent-complete honesty feeds the firm’s cash forecast, and days-to-cash sets how far the firm reaches into its reserves. The Planning Studio (Modules 5 to 6) builds the full planning machinery: baseline curve, labor demand, and the plan behind the invoice schedule. The pipe in this module is the last stage of a plan that started before the first hour was worked.

6

The Owner’s other number

What the building costs: the OPCC

This module follows the Owner’s money, backlog to cash. One more Owner number sits on the PM desk, and it dwarfs the fee. Grace builds a fee, $1.4M on Oakhaven. The Owner asks most often about their building, the ~$40M required to construct it.

Hold two numbers separately. The fee is what Grace earns. The Opinion of Probable Construction Cost (OPCC) is what the building costs. Never blur them. A construction cost number treated casually becomes a liability.

An early schematic number is given verbally, the Owner records it, and nobody revisits it. Design matures, scope firms up, and the estimate climbs. At the Construction Documents phase review the Owner learns the project is 20% over the figure carried for eight months. On a ~$40M building, that is an ~$8M surprise. At that point it is a trust problem rather than a design problem.

The number was never wrong
The early number was never narrowed and never disclaimed. An early cost number is an opinion, not a promise. The Owner will hold Grace to it unless it is narrowed, disclaimed, and reconciled at every phase review.

An estimate is a range that tightens as design resolves

Cost accuracy is a function of how much has been drawn. At Schematic Design the estimate prices intent. By Construction Documents it prices a defined building. Carry the estimate as a band that tightens at each phase review, the cone of uncertainty. State the band and its phase out loud.

The cone of uncertainty: the band tightens as the design resolves −10 / +20% −5 / +15% −5 / +10% market SD DD CD Bid / GMP pricing intent defined systems specified building the market answers
The estimate is a band, and the band narrows as the design resolves. Carry the whole band, name the phase, and it converges on the market answer at bid.
PhaseWhat is being pricedTypical accuracy band*Design contingency*
Schematic Design (SD)Concept, area, systems intent−10% to +20%~15%
Design Development (DD)Defined systems, major materials−5% to +15%~10%
Construction Documents (CD)A fully specified building−5% to +10%~5%
Bid / GMPThe market’s actual answerMarket price→ rolls into Owner’s construction contingency

*Illustrative bands following AACE estimate-class logic. The band tightens as the design resolves. Refer to Grace Legal / General Counsel and the Finance and Accounting Team for project-specific and client-specific guidance for specific scenarios, and to review specific internal policies.

Two contingencies, not one
Design contingency covers what has not been drawn yet, so it shrinks as design resolves. It should approach zero by bid. The Owner’s construction contingency (typically ~5%, and refer to Grace Legal / General Counsel and the Finance and Accounting Team for project-specific and client-specific guidance for specific scenarios, and to review specific internal policies) is separate: it covers change during construction and lives on the Owner’s budget through Construction Administration. Collapsing them into one number hides the risk the project manager is paid to surface.

Say it in writing, every time: the disclaimer

Grace is a design professional, not a contractor and not a cost-estimating firm. Every construction-cost number that leaves the office carries the standard-of-care language in writing.

The standard-of-care line
This is an Opinion of Probable Construction Cost, our professional judgment based on the design at this phase, and it is not a guarantee that bids or negotiated prices will not vary. On larger or more complex work, we recommend the Owner engage an independent professional cost estimator. Grace Legal to confirm the approved wording. Pairs with the Module 4 contract standard.

The disclaimer is the practical form of Protect Integrity: name what the number is and what it is not, so nobody mistakes an opinion for a commitment.

The behavior: reconcile at every phase review

The estimate is a control to run, not a document to produce and file.

Establish Clarity
Every OPCC states its phase, its accuracy band, its contingency, and its date. Issue no number without them.
Control Advancement
No phase review passes without reconciling the current estimate against the Owner’s budget. Where the estimate trends over, trigger value engineering or redesign now, while a change is cheap, rather than at CD, when it is expensive and public.
Protect Integrity
The budget-to-estimate gap goes on the Living Risk Register the moment it opens, with an owner and a next-review date. A cost overrun the Owner learns about at bid is a surprise. An overrun the Owner has watched being managed since SD is competence.
The rule
An early estimate is a promise about process, not a promise about the price. Narrow it, disclaim it, and reconcile it at every phase review.
7

Behavior, not knowledge

Put it to work

On your throughline project, this week:

Backlog is work sold. Cash is work paid for. The float is what the gap between them costs the firm.

Where this connects