No single number tells the truth. Hold all three against each other before calling a task healthy.
Value earned: how much of the work is actually done.
How much budget it took to get there.
Where the project sits against the dates the plan committed to.
Healthy = value earned keeps pace with fee burned, on the planned dates. Any gap is what to examine.
Enter three numbers for a task or phase. The calculator returns the two variances and their indices, with a plain-language read.
A number is data. A number against the plan is information. Always ask “versus what we planned?” on three axes.
Did we earn what we planned to earn by now? (Schedule Variance)
Did the work cost what we planned for it? (Cost Variance)
Are we where the plan said we would be on the calendar?
Keep all three variances small and visible. Untracked drift keeps growing.
Read these together each week. Any one out of line is a prompt to act, and to decide who carries the cost.
The team’s hours are not free to give away. A signal is only worth the action it triggers.