Module 9 of 12 · Managing Execution 2

One Number Will Lie to You

Percent complete, effort burned, and schedule each tell a partial truth. Read alone, any one misleads. Read together, they show exactly where the project stands, in time to act.

Illustrated module guide · the complete walkthrough · companion to the Quick Reference
Where this fitsBehavior Controlling AdvancementOutcome 4 · Sustained Financial HealthLifecycle Execution → Monitoring
Recall · before you begin

Module 8’s business rhythm said to check financial signals every week. Name the signals you would look at, and why “we are 60% done” is not enough on its own.

Read percent complete, effort/fee burned, and schedule together. “60% done” says nothing about what it cost to get there or whether the project is on time. A project can be 60% complete having burned 80% of the fee, on schedule, and quietly losing money.
1

The trap

A single number always tells a flattering story

In Module 8 a project manager set the rhythm that surfaces signals every week. Module 9 is about reading them honestly, turning raw numbers into a true picture of where the project stands, at a point when there is still time to act.

A project manager asks “how is the project?” and usually receives one number. “We are about 70% done.” A figure like that sounds like an answer, and it carries only one dimension of the work. Percent complete with no cost says nothing about margin. Fee burned with no progress says nothing about value delivered. Schedule with no effort says nothing about how hard the team is pulling to hold the date. Each number, alone, tells the most flattering story it can.

Percent complete, burn rate, and schedule only tell the truth when they are read together. One number alone will lie.

The PM’s job in monitoring goes beyond collecting metrics. The job is to triangulate, to hold the numbers against each other until the real story appears.

2

The signals

Which three signals must be read together?

Three signals are blind on their own and honest in combination.

Percent complete

How much of the work is actually done, value earned rather than effort spent.

Alone it lies: “80% done” can hide an 80% over-burn or a slipping date.

Effort / fee burned

How much of the budget has been consumed to reach this point.

Alone it lies: “Only 40% burned” looks healthy, unless only 25% of the work is done.

Schedule

Where the work sits against the dates the plan committed to.

Alone it lies: “On schedule” can mean the team is burning nights and fee to hold it.

?Pause & predict.

A task is reported “on schedule” and “40% of fee burned.” You then learn it is only 25% complete. What is the real story, and is “on schedule” good news here?

The task is burning fee faster than it earns value: 40% spent for 25% done means an efficiency / margin problem. “On schedule” is not comfort here. The date is being held by overspending effort, which will run out before the work does. Read together, the three numbers expose what each hid.
3

The comparison

Why is every signal a plan-versus-actual comparison?

A number on its own is data. A number against the plan is information. Variance, the gap between what was planned and what actually happened, is where the project reports the truth. The discipline is simple and relentless: for progress, cost, and schedule, a project manager always asks “versus what we planned?” A 144k effort is neither good nor bad until the plan shows it was supposed to be 120k.

The variance habit
Planned vs. actual on three axes: value (did we earn what we planned to earn?), cost (did it cost what we planned?), and time (are we where the plan said we would be?). A healthy project keeps all three variances small and visible. A drifting one lets them grow in silence.
4

The instrument

What does earned value measure, in plain terms?

Earned Value is the disciplined way to read those three signals at once. It rests on three measured quantities:

PVPlanned Value

The budgeted cost of the work the team planned to have done by now.

EVEarned Value

The budgeted cost of the work the team has actually completed (% complete × budget).

ACActual Cost

What the completed work has actually cost so far.

From those three, two variances tell the whole story:

Schedule Variance = EV − PV

Positive = ahead of plan on value delivered. Negative = behind.

Cost Variance = EV − AC

Positive = work cost less than budgeted. Negative = over budget for the work done.

That is the entire idea: the two variances ask whether the team is delivering the value it planned (schedule), and whether that value is costing what the plan said it would (cost). The Quick Reference turns this into a calculator a project manager can run on a live task.

5

The example

What do the numbers say about Oakhaven’s Design Development?

Consider the Oakhaven Public Safety Campus from the finance modules. At Design Development the dashboard reads as follows, and the three signals together allow an honest reading:

Design DevelopmentPlanned (earned)Actual (effort)Variance
Value of work done$120k$144k spent−$24k cost
ScheduleOn plan14 days late−14 days
Billing·$41k unbilledat risk

Any single row could be explained away. Together they are unambiguous: the phase earned $120k of value but consumed $144k of effort, is two weeks late, and is carrying $41k it has not billed. That is a phase losing $24k of margin in plain sight, exactly the kind of signal the weekly rhythm exists to catch early.

6

The close

A signal is only worth the action it triggers

Reading the numbers is half the job. The other half is what the Accountable Owner does next: when the team is absorbing client-caused rework on nights and weekends, the owner does not let the hours quietly vanish into the budget. They surface the cause and put the cost in front of the client. The team’s hours are not free to give away. The Coordinator records the overrun. The People Pleaser absorbs it. The Owner converts it into a decision.

Apply on your project

Pick one live task. Pull its percent complete, fee burned, and schedule and read them together, then run the earned-value numbers in the Quick Reference. If value earned trails cost spent, name the action this week: a scope conversation, a staffing change, or a billing catch-up.

Challenge · from memory

?Challenge · from memory.

From memory: name the three signals you read together, and the two earned-value variances and what each one tells you.

Signals: percent complete, fee/effort burned, schedule. Variances: Schedule Variance (EV−PV), value vs. plan. Cost Variance (EV−AC), cost vs. value earned.

The one idea

Percent complete, burn rate, and schedule only tell the truth when they are read together. One number alone will lie.