Module 5 of 12 · Part B · Planning Process

Sequence the Work, Staff the Plan

A budget says how much the work costs. A schedule must still answer when the work happens, in what order, and who performs it. Design work fails on information handoffs far more often than on effort, and Logic-Based Planning sequences the work so the right information reaches the right person at the right time.

Illustrated module guide · the complete walkthrough · companion to the Quick Reference
Where this fitsBehavior Controlling AdvancementOutcome 2 · Controlled, Predictable DeliveryLifecycle Planning → Execution
Recall · before you begin

Part A broke the work down, soft-resourced it, and priced it. Before you can sequence or staff anything, what two products of that module must already be in hand?

The WBS (tasks) and the soft-resource plan (the role and budgeted hours on each task). Schedule and staffing are laid over those.
1

The problem

Why design schedules slip

In Part A the team broke the work down, soft-resourced it, and priced it, and in doing so answered what, which role, and how much. Part B answers the last two questions: when the work happens, and who does it.

Most design schedules open as a Gantt chart full of dates, bars that say when each task is “supposed” to happen. A row of dates records intention rather than the logic that connects the work. When a design project slips, the cause is almost always that someone was waiting on information that no one sequenced to arrive. The architect could not place the floor plan until mechanical sized the equipment, and mechanical could not size the equipment until the owner chose a system.

Consider a patient moving through a hospital, where the journey is a series of handoffs, from intake to triage to imaging to surgery, and a delay anywhere stalls everything after it. A design project carries the same shape: the project is the patient, the disciplines are the caregivers, and what moves between them is information. Sequencing the handoffs is therefore what produces a schedule that holds.

Design work flows on information, not effort. Sequence the information, and the work follows.

That is Logic-Based Planning: rather than guessing dates forward, a project manager starts from the deliverable and works backward, sequencing the flow of information so every task has what it needs the moment it needs it.

?Pause & predict.

A PM builds a Gantt chart, assigns every task a start date, and emails it out. Two weeks in, structural is idle. Nobody missed a date. What did the Gantt chart fail to capture?

The dependencies between disciplines, who needs what information from whom, and when. Dates alone do not show that structural cannot start until the floor plan exists. Logic-Based Planning sequences the handoffs, not just the dates.
Planning Studio · Pick up where you left off

Planning Studio 2 opens with the plan you committed in Part A, your WBS, your hours, and your margin, and walks it through everything this module teaches: milestones, protected QAQC periods, a backward-built network, the Gantt, the Earned Value Plan with its labor demand, and the S-curve. If you have not finished Studio 1, the tool sends you back, or hands you the plan Grace filed in BST. Open Planning Studio 2 →

2

The frame

What planning optimizes

What three plans run at once, and what constrains each?

Every project plan is really three plans at once, and the PM’s job is to keep them in balance. Each one carries a constraint, and good planning focuses effort on releasing the binding constraint while keeping the team moving toward the goal.

Financial planning

The budget and cash flow, the pattern of how money will be spent over the life of the project.

Constraint · the fee available

Task planning

The completion of work, both what work will be done and when it will be done.

Constraint · the work to be done

Resource planning

How the project will be staffed, the relative labor demand across the schedule.

Constraint · the people available

Part A built the financial plan (the budget) on top of the task plan (the WBS). This module adds the schedule to the task plan and then lays the resource plan over both. The art is sequencing the work so the binding constraint, usually a piece of information or a single over-booked person, is released before it stalls the team.

3

The method

Logic-Based Planning

How do the five frameworks run from phase to week?

Logic-Based Planning (LBP) ensures design teams work to the logical flow of information between disciplines. It runs in five frameworks, sequenced from the whole phase down to this week’s work, each one keeping the team aligned to the deliverables that matter.

1

Phase Milestone Planning

Set the overall phase schedule and define what “done” means for each deliverable, using a Deliverable or QA checklist.

2

Intermediate Milestone Planning / Pull Planning

Find the checkpoints inside a phase (30 / 60 / 90%). Separate deliverables from information, list each discipline’s needs and provides, and reverse-sequence to the critical path.

3

Biweekly Work Planning

Each discipline plans its own parallel work in rolling two-week increments, aligned to the milestone plan.

4

Information Flow Management

Move the right information between disciplines on time, so no one stalls waiting.

5

Work Plan Review

Revisit and adjust the plan on a regular cadence, since planning is a continuing process.

The goal

Visualize the flow of work so the team is prepared to complete the right work, with the right people, at the right time, at the optimal cost, and efficiently advance the project.

4

The core skill

Pull Planning

How does planning the work in reverse find the start date?

Pull Planning builds the schedule backward from a milestone rather than forward from a start date. A project manager starts at the end, the deliverable that must be true at, say, 30% Design Development, and asks one question over and over: “What is needed immediately before this, in order to deliver it?” Each answer is a handoff: one discipline needs something, and once they get it they provide something to the next, in a stated duration. Those chained handoffs are the critical path of information.

The discipline is to separate deliverables from information, and to phrase every link the same way: “In order for me to provide X, I need Y. Once I have it, I will provide X in N days.” Step back through an Oakhaven 30% DD milestone and watch the chain assemble and the start date reveal itself:

Milestone · 30% Design Development (Oakhaven dispatch facility)
Click Pull back one step to reverse-sequence the work from the milestone and find when the first decision must happen.

Working backward, the chain reveals that the owner’s system selection is the true start of this milestone, and since the owner needs a review window, the initiating act is the PM putting three system options in front of the owner about three weeks before the deadline. Forward planning never surfaces that decision, and backward planning puts it first.

?Pause & predict.

The pull plan shows the owner must pick a mechanical system 3 weeks before 30% DD. The owner is “not ready.” What does the Accountable Owner do?

Surfaces it now, in writing, as the binding constraint, with the downstream cost of delay made explicit. The whole point of pulling backward is to expose the decision that governs everything while there is still time to force it.
Planning Studio · Stage 3 · Pull Oakhaven backward

Reverse planning stops being abstract in Segment 3a: submission is contractual at Week 13, the QAQC weeks are already reserved, and you sequence 13 production packages backward by asking what must exist first. The checker knows the prerequisite network and your milestone deadlines, so placing plan development too late makes it name the week the phase breaks. Set the 50% progress set before Week 6 and it proves the promise cannot be kept, since four weeks of floor plans plus a QAQC week do not fit. Finding that now rather than in December is the point. Work Segment 3a →

5

Make it visible

Swim lanes & biweekly plans

Which board carries the handoffs, and which carries the week?

The critical path of needs and provides is best drawn as a swim-lane diagram: one lane per discipline, time across the top, and the information handoffs flowing between lanes. It shows who initiates each handoff, who receives it, and when each handoff is due, all on one page.

Swim lanes · flow toward 30% DD → Owner Mechanical Architecture Structural System selection Equip & room req'ts Floor plan Shear-wall locations 30% DD
Each arrow is a handoff. The owner’s decision feeds mechanical, mechanical feeds architecture, and architecture feeds structural, and only then is the milestone reachable. The late lane is the lane to manage.

The swim-lane plan deliberately shows only the shared, critical handoffs, the items with the greatest impact on the whole team. The parallel work inside each discipline lives in a Biweekly Work Plan: each group pulls its own tasks back from its milestone commitments and plans in a rolling two-week look-ahead. Each group drops the finished week, confirms the next, and adds one new week. That rhythm keeps the milestone board clear while every discipline still sees the whole.

Planning Studio · Segment 3b · The board to post

When your network holds and you lock the schedule, the Studio re-sorts it into the Gantt: first-to-start on top, last-to-finish at the bottom, QAQC weeks hatched, milestone weeks flagged. Same data and zero edits, and the sequence logic becomes a wall schedule. Adjust the network and the board re-sorts itself.

6

The last question · Who?

Staff the plan

How does role demand become real people and a measure of progress?

The schedule tells the team when, and the soft-resource plan from Module 5 tells the team which role. Laying one over the other produces a resource heatmap, a count of how many hours of each role the project needs, week by week. That demand stays abstract until the team moves to hard-schedule it: assign real people, and confirm that the person required is not already booked solid elsewhere.

Role demandWk 1Wk 2Wk 3Wk 4Wk 5Wk 6
Senior Architect40288
Architect1030383018
Project Manager61416263416
Principal (QA)461222
The table shows the plan expressed as role demand over time, week by week. Orange peaks are where a real person must be confirmed free, and hard-scheduling turns this grid into names and catches the over-allocation before it becomes a missed deadline. This is the bridge to firm-level utilization.

The work, the hours, and the schedule combine into the one instrument the PM works from every week, the Earned Value Plan. A Gantt of the sequenced work, weighted by each task’s share of the fee, produces a curve of how much of the fee should be earned by each point in time. It is the roadmap that answers, every week, the Module 3 question: is the team earning value as fast as it is spending effort?

0% 25% 50% 75% 100% W1W2W3W4W5W6W7W8Phase timeline → Planned % of fee earned 30% DD Earned Value Plan · the PM’s progress roadmap
Each waypoint is where the team should be. Tracking actual earned value against this line shows drift in the week it starts rather than in the month it costs money.
Planning Studio · Stages 4 to 5 · Demand, the fix, and the line

This is where the Studio closes the loop. The EV Plan spreads your $280,000 across your schedule, and the labor demand table converts it to hours per role per week, so with the filed plan both designers run 48 to 53 hours through Weeks 9 to 11. A plan that needs 1.3 designers per seat is a plan no roster can staff. One click, Redistribute labor and maintain performance, moves the overage to the Project Architects at cost parity: same dollars, same weeks, margin untouched, and everyone under 40. Then the S-curve draws, the line you manage to, with your milestones on it. Work Stages 4 to 5 →

7

The close

Planning as a continuing process

A pull plan, a swim-lane board, and an Earned Value Plan are working documents that the team maintains through the phase. The whole point of Logic-Based Planning is that it stays alive: the team revisits the milestone plan and its biweekly work plans on a regular cadence, adjusting as information arrives and constraints shift. The Accountable Owner owns that rhythm, appointing a keeper of the plan, distributing it, and protecting the review.

Sequence the information, staff the flow, and keep the plan current, and a budget becomes a delivered project.

With Module 5, planning is complete: the work is broken down, priced, sequenced, and staffed, with a roadmap to measure it against. Next comes Communication Planning, deciding how the team, the consultants, and the client will stay aligned around this plan, and then the kickoff, where both plans are presented to the project team.

Apply on your project

Take one upcoming milestone on a live project. Pull-plan it backward: pick one deliverable, ask “what is needed immediately before this?”, and keep pulling until you reach the first decision that governs everything. Put a date on that decision, and protect it.

Challenge · from memory

?Challenge · from memory.

From memory: does Pull Planning sequence dates or information? And what is the one question you repeat as you pull backward?

It sequences information, the handoffs, not dates. The repeated question: “What is needed immediately before this, in order to deliver it?”

Module 5 · Part B throughline

Design work flows on information, not effort. Plan it in reverse, make the handoffs visible, and staff the flow, and the schedule holds.

Planning Studio · The plan becomes the system of record

The Studio ends the way real phases begin: your plan rendered on BST screens, covering WBS and fee allocation, the resource plan, and the EV baseline, so the plan lives in the system of record rather than in a workshop file. Load it, post it, then run the cadence this section describes: earned vs. planned, cost vs. earned, every reporting period. See your plan in BST →