Module 4b · Quick Reference
Reference cards for owning the project and the first client conversation.
Module 4b throughline: You earn the right to lead a project by understanding the project you have stepped into, well enough to explain why every decision was made, take a view on whether it still holds, and say what winning will require.How to reconstruct the pursuit
Card 1 · the upstream review
A project reaches the PM only after it clears the Go / No-Go: the review every opportunity passes through during Pursuit, upstream of Contracting and the PM step-in. It is led by the Principal in Charge in concert with Business Development. A PM may take part in the call and inherits its result. Use this card when asked to weigh in.
The scoring chart, the way Grace runs it. Below is the firm’s tool, filled in as a worked example of how the chart scores a pursuit. The left column maps each row to the three factors above.
| Relevant Factors | Factoring Scoring Scale | Score | |||
|---|---|---|---|---|---|
| NEGATIVE (0 to 1 POINTS) |
NEUTRAL (2 POINTS) |
POSITIVE (3 POINTS) |
|||
| Factor 1 Relationship strength |
Are we known by the Owner / Decision-Maker? | Unknown to this Owner / Decision-Maker (0) | Known, but not fully cultivated | Well-developed working relationship | 2 |
| Factor 2 Preparedness |
Is this the first we have heard of it? Was it on our “Top 10” List? | Did not know until the RFQ/RFP came out, unprepared (0) | Known or on Top 10 List, but no pre-sale meeting | On Top 10 List, capture plan completed | 3 |
| Factor 3 Qualifications & timing |
Do we meet the RFQ qualifications for portfolio and team? | Capable (1) | Can meet or exceed every requirement | Technically superior, our sweet spot | 3 |
| Does marketing have adequate time for a tailored submission? | One week or less to due date (0) | Two weeks or less to due date | Over 2 weeks to due date | 3 | |
| Total score | 11 | ||||
The Pursuit-stage process. The review kicks off a sequence led by the PIC and BD. Below is the order it runs in and where a PM takes part.
Source: Grace Pursuit roadmap (Milo) & the Go/No-Go Decision Scoring Chart. The chart above reproduces the firm’s tool. The example scoring is illustrative.
See the Pursuit & Go/No-Go FAQ →Card 2 · the output
Build this at step-in. It is the PM’s first deliverable. Eight fields, recovered from the Marketing Folder and the PIC. State why we chased it, why we won it, and what was promised, assumed, priced, and at risk, in your own words and backed by evidence. Any field you cannot state is your next conversation.
What made this opportunity worth pursuing.
From: Go/No-Go record, Marketing Folder.
What differentiated Grace and earned the client’s decision.
From: proposal, Marketing Folder, PIC.
Scope and deliverables the PM now owns.
From: prime agreement, proposal.
Fee basis, staffing, and scope assumptions behind the price.
From: fee buildup, pursuit team.
The fee, and where the margin sits.
From: BST, fee basis.
Priorities carried out of pursuit, in their words.
From: pursuit team, discovery.
Gaps, outdated assumptions, and exposures already visible.
From: your read of fields 1 to 6.
The short list to close before planning advances.
From: fields 6 and 7.
Step-in is complete when the PM can explain why it was chased, why it was won, what was sold, what assumptions the fee depends on, what the client expects, where the risk sits, and what must be clarified before planning advances.
Card 3 · the inventory
Every gap has an owner. Before asking the client anything, ask this first: is the answer recoverable from the record, or does it exist only with the client? If it is recoverable, confirm it. Pull it from the record. If it is not recoverable, discover it. This requires the client’s own words (see Card 4).
Where each piece lives:
Card 4 · into the room
This step is ③, discover current reality. On Oakhaven, one call with the Owner’s Rep, Karen Whitfield, made both halves of value concrete: Performance meant the 911 dispatch center could never go dark during cutover. Experience meant she could never be surprised at her City Council briefing. Neither line was in a document. These questions are built to find that target.
The contract: what must be delivered.
What the client will actually call success. Discovery finds the distance between them.
“A year after these doors open, what has to be true for the people who use this space, and how will you know?”
Probe: what does this make possible that was not possible before?
“Who lives, works, heals, learns, or gathers here every day, and what do they need that they would never put in a brief?”
Probe: whose experience must this get right above all?
“Where would ‘good enough’ be a failure, the few things we must protect at all costs?”
Probe: if we could guarantee only three outcomes, which three?
“When scope, schedule, and budget collide, which do you most want us to protect?”
Probe: where would you welcome ideas to save cost or time?
“Beyond you, who has to believe this succeeded, and what will they judge it on?”
Probe: where are those stakeholders not yet aligned?
“How, and how often, do you want to hear from us, and what does a great update look like?”
Probe: what makes you trust an update from a design team?
How to use it, the Grace way:
Card 5 · defend it
Before planning, defend the understanding to the Principal. Seven questions: four recovered from the record, two discovered from the client, one final check. Understanding is complete when the assumptions run out, not when the questions do.
What was promised: state the scope in one sentence.
What was assumed: what does the fee depend on holding true?
What was priced: where does the margin actually sit?
Why we chased and won this work: what does the record say the client is really buying?
What does Performance mean on this project, in the client’s own words?
What does Experience mean on this project, in the client’s own words?
What is still unclear or stale, and what will be done about it before planning?
The Principal concedes when the evidence earns it. The test is whether the understanding holds up. Fields recovered without evidence, or discovered without the client’s own words, do not pass.
Module 4b · Project Startup
“The Project Plan is the evidence that ownership already happened. Ownership begins before it.”
Understand what you own, build your Review, find the finish line, defend it, then carry what you learned into the plan.