The Contract Process: A Project Manager’s Field Guide

Everything a PM needs to run contracting on a project: how a contract moves, who owns each step, the rules that cannot be broken, the terms to defend, and where every document lives. The Contract Team handles the legal work. Feed the process cleanly, decide on time, and do not let project work run ahead of the contract.

Version 2.1 Updated June 30, 2026 Maintained by the Contract Team Source: Contract Procedures & Workflow
← Back to Module 4 · Quick Reference Guide
1

Purpose & How to Use

What this is, and how to use it

This is the single reference for how contracting works at Grace, written for project managers. Use it when starting a project, when a client sends their own contract, when a consultant needs to be brought on, or any time the next step is unclear.

  1. New here? Read the Golden Rules first. These rules protect the firm. Breaking one creates real exposure.
  2. Not sure where you are? Use the “Which track am I on?” router, then follow the PM spine for your part.
  3. Need the detail? The three process tracks show every step. Tap any colored step for what it requires.
  4. Negotiating with a client? Jump to the Six Provisions cheat sheet: plain-English on each term and Grace’s position.
  5. Need a form, a signer, or a contact? It is all in the Directory. New term? See the Glossary.
Maintainer note: wire the three Quick Links above to live URLs before publishing. Contracting is migrating from Milo to Monday CRM. Where this guide says “Milo,” use Monday CRM once that switch is live.
2

Golden Rules

Never break these

Know these six. They protect the firm and the client.

3

Start Here

Which track am I on, and what is my part?

Three situations cover almost everything. Pick yours, then follow the PM spine below for the steps that are your responsibility.

When in doubt, submit the request on Milo and ask the Contract Team. Starting the tracked process early is always better than guessing.

The PM spine: six jobs, in order

4

The Process

How a contract moves, start to finish

Color shows who owns the step (each carries an initials badge so it reads in grayscale too). Shape shows the kind of step: rounded ends are start/finish, rectangles are actions, amber diamonds are decisions.

Every contract starts the same way All requests originate in Milo (“Request a Contract”). Milo automatically creates a tracked item on the Monday.com · Legal Requests board, so the whole team can see status and priority without an email bottleneck. No Milo request means the Contract Team cannot see it, and it does not happen.
Plan your timing Submit as early as possible. Priority is set on the Monday board, and turnaround depends on the queue and complexity. Standard lead times are still being finalized by the Contract Team (placeholder, confirm and insert per track). The only hard clock today is Code Red: a genuine deadline within 3 business days. Late planning is not an emergency. Build contract time into the schedule from the start.
A

Grace issues an AIA Owner / Architect contract

We write it on our paper ⏱ Lead time: confirm w/ Contract Team
B

Reviewing an Owner-provided contract

The client hands us their paper ⏱ Lead time: confirm w/ Contract Team
!
Code Red: only when it is truly urgent A genuine, non-negotiable client deadline within 3 business days with real revenue or liability at stake, or a material legal/compliance exposure. Late prep by the project team does not qualify. To declare: email Zeb Scott & Caitlin Burcham, subject “CODE RED : [Contract/Project]”, include contract type, counterparty, reason, the true deadline, and all drafts/exhibits. Then ping them on Teams or call.
C

Issuing a Consultant / Subconsultant contract

We hire the consultant on our paper ⏱ Lead time: confirm w/ Contract Team
After signature: every track ends here The Contract Team saves the fully signed contract to the project folder on the server and the Project Accountant is copied. From there, change orders & pay apps are handled by the Admin Team (under Admin Director Deondra Brewington-Bierria) through their own Milo request forms. The project team saves those to the server and notifies the accountant.
In flux · ties to Construction Administration: change orders, additional services, and pay apps after signature carry over into the Construction Administration portion of the training. That content is still being finalized. Treat this as a placeholder for now.
5

The Negotiation Cheat Sheet

The six priority provisions

When we review a client’s contract, these are the six terms we care about most, reviewed carefully by the Contract Team. The Contract Team redlines them. A project manager must recognize them and be able to explain Grace’s position to a client. Each card: what it is, why it matters, and the ask.

6

Pursuits

RFQ contract reviews

Pursuits carry their own timing constraint. The moment an RFQ involves a contract, loop in the Contract Team. Action at this stage protects or forfeits our ability to negotiate later.

What to confirm early

  • Is a contract provided for review? When is it due?
  • Is there a Q&A window? Often the only chance to request modifications. Timing is critical.
  • Will requesting changes disqualify us?
  • If it says “no changes allowed,” we still review and decide whether to proceed, then negotiate if awarded.

If changes will not disqualify us

Have the Contract Team add a blanket reservation-of-rights statement to the submission, so we keep the right to negotiate the terms that matter after award.

Use the exact language at right →

Blanket reservation-of-rights statement · use verbatim
If awarded, Grace reserves all rights to negotiate reasonable terms of any ensuing agreement, including but not limited to provisions addressing an applicable standard of care, limitations of liability, waiver of consequential damages, indemnity, Architect/Design Professional's work product and other standard contractual protections requested of an Architect/Design Professional and its insurer.
7

Bringing on Help

Subconsultants

We hire consultants on our paper, never theirs. Get them into the system early and keep their insurance current, or payments stall.

When to act

  • As soon as you know a consultant is likely, list them in Milo under the owner contract request (“Consultants” is required info). The listing populates the Monday board so the Contract Team can plan.
  • When ready to engage them, submit a separate Consultant Contract Request on Milo.

What the request needs

  • Consultant name & discipline
  • Scope and fee
  • Basic service vs. reimbursable
  • A copy of their unsigned proposal (reference only)
!
The two hard rules 1. Never sign a consultant’s proposal, and never let anyone else sign it. Grace issues its own AIA agreement.  2. Consultants are not paid until our contract is signed, a current COI is on file, and the agreement is saved to the project folder.

Required documents back from the consultant

W-9

Sent to Clint Skinner.

Current Certificate of Insurance (COI)

Filed on the Monday.com COI tracker for expiration tracking. Project Accounting confirms it before any payment. no current COI, no payment.

Pass-through vs. reimbursable: know the difference

Pass-through

Invoices are passed to the Owner, who pays the consultant directly. The money does not flow through Grace.

Reimbursable

The consultant (often Owner-provided) is retained by Grace, and the Owner reimburses Grace for the cost. A contract between Grace and the consultant, typically a C402, must be in place before payment is released.

Master agreements & task orders

The Contract Team is compiling all existing and legacy subconsultant master service agreements (MSAs), plus a wish list of MSAs we want to have. The more MSAs in place, the faster we can issue task orders for future work instead of renegotiating from scratch. Once the master list is compiled, it will be published on Milo. Check there before assuming a consultant needs a fresh agreement.

Check first: is an MSA in place? Before issuing a consultant contract, confirm whether a Master Service Agreement already exists with that consultant. If none is in place, submit the request on Milo and ask the Contract Team to begin an MSA.
Assignability language in Grace ↔ Consultant master agreements (C421) · example
The Architect may assign any Service Order/Letter Addendum, or any portion thereof, to an affiliated entity without the prior written consent of the Owner/Consultant, provided that such affiliated entity agrees to be bound by the terms and conditions of this Agreement. The Architect shall notify the Owner/Consultant in writing of any such assignment. The Owner/Consultant agrees that its obligations under this Agreement shall continue in full force and effect as if such assignment had not occurred.
8

Who Does What

Responsibilities in shepherding the process

Same colors and initials as the flowchart. The Contract Team does the legal work. The process moves at the speed of the PM. Read your own card first, then know your touchpoints with the rest of the team.

9

Directory

Systems, forms, signers & contacts

These systems carry the whole process. Use the right system for each request to avoid losing a document or stalling a payment.

Check your contract status here Track any contract, any time, on the Monday.com · Legal Requests board. Every Milo request lands here automatically, showing status and priority for the whole team. Check the board regularly rather than emailing for updates. (Consultant COIs live on the separate COI tracker board.) Open the Legal Requests board ↗

Template library: which form, when

If the client does not supply their own form, the Contract Team uses these AIA templates (with Grace’s standard modifications already built in).

Authorized signers

PMs are not signers. Nothing is signed without routing through the Contract Team first. Only the people below may execute. Verify the current list with the Contract Team before relying on it.

Authorized Signors · updated per May 2026 Resolution The authorized-signor list was revised by the May 2026 Resolution. The names below reflect the prior version and are superseded. The official updated roster is pending. [PLACEHOLDER · replace with the May 2026 Resolution list once received.] Until then, verify any signer with the Contract Team before relying on it.

Authorized company signors

  • Gerald D. Hebert, II
  • Adam L. Fishbein

Authorized contract signors

  • Gerald D. Hebert, II
  • Adam L. Fishbein
  • David F. Hebert
  • Thomas D. Curtis
  • James E. Spencer
  • Larry W. Adams, Jr.
  • Robert G. Maggiore
  • Eric L. Hahnfeld
  • Kevin Williams
  • Daniel Summers
  • Christopher Chivetta
  • Erik Kocher
  • Vispi Karanjia
  • Erik Clinite
  • Walter Powell
  • Timothy Hoeft
  • Sandra Goodman
  • Rolf Haarstad

Contracting entities

The Contract Team decides which Grace entity signs. The order of preference is below. (Entries marked “Why?” are open items in the source to be confirmed.)

Grace Design Studios, LLC (LA)Primary
Grace Design Studios, LLC (DE)Secondary Ownership requirements
Grace Design Studios, PLLC (MS)Ownership/Structure states
Grace Healthcare Studios USA, LLC (AZ)Last resort Why? Confirm with Zeb

Who to call

10

Plain Language

Glossary

The terms in this process, in everyday words.

← Back to Module 4 · Quick Reference

Appendix: step-by-step detail