Module 11 of 12 · Quick Reference

The Construction-Admin Map

One reference card for construction administration, the full lead-vs-verify split across every CA document, from pay applications to closeout.

Module 11 throughline: Lead the calls only judgment can make. Verify the process with Admin. Confusing the two means delegating judgment or taking on Admin process work.
Async + VirtualQuick ReferenceConstruction Administration
Where this fitsBehavior Protect IntegrityLifecycle Construction AdministrationCompanion to Module 4 · Lead vs. Verify
1

Quick Reference · the CA map

Lead vs. Verify · the construction-phase reference

Module 4 taught the principle with startup-stage examples. This is the full construction-phase application, the same lead-vs-verify split across the contract-administration documents. LEAD the judgment. VERIFY the process, prepared and finalized with Admin. Keep this open on the job.

CA taskPM LEADS (judgment)Verify / Admin (process)Document · system
Pay ApplicationsReview the application, evaluate actual progress, certify the amount due.Review front-page number, apply signature, send with standard language.AIA G702/G703 · Project Server
ASIIssue minor clarifications that do not affect contract sum or time.·RFI log/form · CenterLine
Proposal RequestsRequest pricing for a potential change before deciding to proceed.·Template via Milo · CenterLine
Change OrdersReview/process formal changes to scope, cost, and/or time. Owner, contractor, architect sign.Review number, signature, standard language.AIA G701 · CenterLine
CCDDirect changes when cost/time is not yet agreed, so work can proceed.Review formatting, signature, standard language.AIA G714 · CenterLine
Substantial CompletionInspect, determine substantial completion, prepare the punch list, set warranty start.Admin prepares. Architect reviews. Admin signs & sends.AIA G704 · Project Server
Final CompletionVerify punch-list completion. Review closeout, warranties, O&M, as-builts, lien waivers. Recommend final payment.Admin prepares. Architect reviews. Admin signs & sends.Letter · Project Server
RFIsRespond to contractor questions on drawings, specs, coordination.·CenterLine
SubmittalsTo discuss: role split not yet defined.To discussCenterLine

The change chain: field condition → RFI → clarification/ASI → (if cost/time impact) PR → contractor proposal → CO (agreed) or CCD (not yet agreed, work proceeds).   Closeout: inspect → punch list → G704 → verify punch items → review closeout docs, warranties, O&M, as-builts → confirm lien waivers → recommend final payment.

Module 11 · Construction Administration

Lead the calls only judgment can make. Verify the process with Admin, document by document, from pay applications to closeout.