Part 1 set the boundary and the budget. Now the same plan becomes a schedule: milestones, protected QAQC periods, and a backward-built network. Then it becomes an Earned Value Plan with its labor demand, and finally the S-curve, the line you manage to.
Oakhaven Public Safety Campus · GRC-26-0142 · Design Development · Nov 8, 2026 to Feb 6, 2027 · Grace phase fee $280,000Project Schedule
A schedule is built in passes, in order. Segment 1: plant the major milestones. Segment 2: back up one week from each milestone and reserve it as the QAQC period, closed to production work. Segment 3a: working backward from each milestone, sequence the work packages by what must precede what, until you have a logical network of tasks and handoffs. Segment 3b: when you lock the schedule, the Studio re-sorts your network into the Gantt chart you would post on the wall.
The submission date is contractual: Feb 6 (Week 13), and it is locked. Place the other two: click a week. The 50% progress set is what your consultants coordinate against, and the reconciled estimate is what lets the Owner say yes.
Nothing goes out the door without review, and review that is absent from the schedule loses to the deadline it was meant to protect. One click reserves the week before each milestone.
Click a week in a row to set that package’s start, and the bar draws at its planned duration. Ask of every package: what must exist before this can begin? The checker knows the prerequisite logic and your deadlines, and it will name where the network breaks.
Earned Value Plan
Now the three artifacts merge. Each deliverable carries a share of the $280,000 fee, weighted by where the effort actually sits (your budget is the evidence). The Studio then spreads each deliverable’s fee across the weeks your schedule says the work happens. The result is planned value by week: the Earned Value Plan. Weights must total 100%, since every dollar of fee lives somewhere in the WBS.
Planned value per week, $000s. Amber bars fall in QAQC periods, where the effort is review rather than production.
The EV Plan implies a staffing plan: each role’s budgeted hours, distributed the way the planned value lands. Highlighted cells exceed 40 hrs, meaning more than one full-time person in that role that week. Each one is a staffing decision to make before the week arrives.
Earned Value S-Curve
The cumulative EV Plan against the $280,000 phase fee is your S-curve. This is the line you manage to: each reporting period, plot fee earned against it. Ahead of the line with costs in check, your margin is safe. Below it, you know the week the drift started rather than only the week the phase ends.
System of Record
The Studio taught the logic, and BST is where the plan lives. WBS 1.5.2.1, "Load fee & budget in BST", is a working step. Once your plan is in the system, every timesheet posts against it and every invoice draws from it. The margin gap then becomes visible the week it opens. Below is your plan, exactly as it reads once it is built in BST.
Screens simulated for training, a Grace Design Studios PM Excellence Academy exemplar. Values shown are your committed plan.