TECHNICAL SESSION · LIVE · 60 MIN · HANDS ON

Run the Monthly Cycle in BST

Session job aid. Keep this open during the working session.

Session Home  ›  Quick Reference

Use this page to run one monthly accounting cycle. Four dates, one review, and one scorecard read. Work the dates in order and the numbers arrive in time to act on.

The monthly clock

Two of the four dates sit inside Grace. The first belongs to the consultant and the last belongs to the client.

DateWhat happensWhat slipping it costs
By the 20thConsultant pre-bills reach Grace. Illustrative, confirm per agreement.A consultant who bills late makes Grace late. The review opens without the lines it has to verify.
By the 25thPre-bill review. Right phases, clean descriptions, backup attached, consultant lines verified.Errors reach the client rather than being resolved inside Grace. Most disputes originate on a sloppy invoice.
By the 7thInvoice out.Work already earned stays in Aged Unbilled and ages another month before it can be collected.
Net-30Payment falls due 30 days from the invoice date.The collection clock starts at the invoice date. A late invoice carries the due date with it.
Run the pre-bill review before the 25th

Four criteria define the review: right phases, clean descriptions, backup attached, consultant lines verified.

  1. Right phases. Every line sits in the phase where the work happened. A charge in the wrong phase misreports two phases at once.
  2. Clean descriptions. Each line describes the work in the language of the agreement, so the client’s reviewer recognises what is being billed.
  3. Backup attached. Reimbursables, consultant invoices, and whatever else the agreement requires travel with the invoice.
  4. Consultant lines verified. Review consultant invoices like internal pre-bills: right phase, right amounts against their agreement, clean backup. A disputed consultant line holds the entire invoice.
  5. Retainage checked against the agreement. Some agreements hold 5 to 10 percent of every invoice. Confirm the held percentage matches what was signed.
  6. Resolve, then release. A line questioned inside Grace costs an exchange of email. The same line questioned by a client holds the whole invoice until it is answered.
Read the scorecard in this order

The read has a fixed order. Run it at project level, then run it again at phase level.

ReadWhat it isWhat it says
1 · RevenueRecognized revenue to dateWhat the project has earned
2 · EffortAmount spent to date, valued at billing rate rather than at raw costWhat the project has spent
3 · VarianceRevenue minus EffortThe live margin. Negative means effort is outrunning revenue
4 · Effort Performance IndexRevenue divided by EffortAbove 1.0 is healthy. Below 1.0 means effort is outrunning revenue
5 · ProfitThe fee minus the EAC at today’s paceA projection rather than a record
The calculations behind the columns
Variance = Revenue − Effort
Effort Performance Index = Revenue ÷ Effort
EAC = spend to date + the estimate to complete
Profit = the fee − the EAC at today’s pace
Estimate to complete, pace holds = spend ÷ the percentage truly complete
Days to cash = Unbilled Days + Receivable Days
Oakhaven at the data date

Illustrative training data on the locked Oakhaven fee. A single phase can read red while the project total reads green.

ColumnProject totalConstruction Documents
Effort % Complete60.571481.6327
Revenue % Complete61.428661.2245
Effort Performance Index1.01420.7500
Variance12,000.00−100,000.00
Variance At Completion18,666.67−163,333.33
Re-forecast on three triggers

A forecast stops being true at identifiable moments. The course names three.

  1. Variance runs negative two reviews in a row. One bad week is noise. Two is a trend with a cause.
  2. A phase review, a priced scope change, or a staffing change. Each one changes the work the remaining fee has to cover.
  3. Percent complete gets re-based. A new percentage against the same spend produces a new estimate at completion.
The four recovery levers, in order

The order matters more than the list. Each lever changes what the next one has to do. The course lists hope as the fifth item and names it the one non-lever.

OrderLeverWhat it changes
1Close the open decisionStops the rework that is generating the spend
2Restaff to the ratePuts the remaining work at the rate the fee supports
3Re-scope the remaining work to the remaining feeMatches what is left to do to what is left to spend
4Price what changedRecovers the scope the client added after the fee was built
Days to cash, in two halves

Unbilled dollars convert to cash by being invoiced. Aged receivables convert by being collected.

UNBILLED DAYS

Measures. How long earned work waits before it reaches an invoice.

Range. On the rhythm, single digits to about 15. Drifting, 45 or more.

Oakhaven. Construction Documents carries 21. Five tasks over 30 days total $39,950.00.

Converts by. Invoicing, the fastest cash the firm can raise.

RECEIVABLE DAYS

Measures. How long a sent invoice waits before it is paid.

Oakhaven. 42.00 at the data date, with GRC-26-0142-008 at $31,200.00 and GRC-26-0142-006 at $14,600.00, $45,800.00 in total.

Converts by. Collection, on the ladder below.

DAYS TO CASH

Measures. Unbilled Days plus Receivable Days.

Span. Work to cash runs 60 to 90 days, against payroll every 14 days and $230k to $350k of float carried on roughly $115k earned per month.

Owner. The first half belongs to the project manager.

The AR escalation ladder

The project manager holds ultimate responsibility for AR collection. Read the BST aging report and the collection notes before contacting the client.

Days outstandingWhat happensWho acts
Day 1Invoice tracked in BST.Project Manager
Day 7 to 10Receipt check with the client.Project Manager
31 to 45Friendly check-in. AP follow-up. Document in BST.Accounting contacts the client’s Accounts Payable department beginning at 31 days
46 to 90Day 45, the specific ask. Day 60, the call, with the PIC aware.Project Manager
91 to 120Formal engagement once an invoice passes 90 daysPractice Leader
Over 120Reviews the invoice and determines whether additional escalation or legal action is appropriateExecutive Leadership
On a live project

What to do

  • Chase consultant pre-bills ahead of the 20th.
  • Check the pre-bill against all four criteria before the 25th.
  • Resolve a questioned line inside Grace, then release the invoice.
  • Send the invoice by the 7th.
  • Read Variance beside the Index at phase level as well as project level.
  • Add Unbilled Days to Receivable Days and write the total down.

What to watch for

  • A phase Index below 1.0 sitting under a project total above 1.0.
  • Variance negative two reviews in a row.
  • Work that became billable more than 30 days ago sitting in Aged Unbilled.
  • A retainage percentage that does not match the signed agreement.
  • A consultant invoice that arrives after the review has opened.

What to avoid

  • Releasing a line no one inside Grace has verified.
  • Reading the project total alone.
  • Forwarding the aging report to accounting and considering it handled.
  • Working the recovery levers out of order.
  • Treating hope as a lever.
  • Working to the 20th without confirming it against the executed consultant agreement.

Bring last month’s pre-bill and the date the invoice actually went out. The Session Overview lists what the course never supplied, including the Bills inquiry the whole review runs on.